In late 2024 LGM Industries was contracted to remove, replace and reinstate a vessel for a large silicon manufacturing company.

The scope of works for this project included:

  • Disconnection and removal of the burner assembly, combustion air ducting and associated valves, outlet hot air ducting, exit ducting to stack, and other associated equipment
  • Removal of platforms attached to the vessel shell
  • Temporary removal of equipment, flooring and structural steelwork
  • Cutting and removal of vessel sections
  • Installation of vessel sections
  • Welding-out of vessel sections
  • Reinstatement of the structure and equipment

LGM was also tasked with fabricating two new vessels for the client which were then installed by us onsite.

 