LGM Industries was engaged to supply and install the piping, electrical, concrete and structural components necessary to operate the SSA Anti-Caking system, supplying propylene glycol to Trains 1 and 2.

The Albemarle Kemerton Plant will include a processing facility to deliver new battery grade lithium hydroxide monohydrate (LiOH.H20).

 

LGM’s scope of work included:

  • Supply and install concrete bund, footings and pipe, and IBC pedestals.
  • Install the SSA Anti-Caking system including loose tanks, MCC, interconnecting piping and cabling within the system.
  • Install the sump pump and discharge pipe (including support of the discharge pipe on the pipe rack).
  • Install the piping and in-line items to existing Sodium Sulphate screw conveyors.
  • Fabricate and dosing hatch on to the existing screw conveyor casings.
  • Install the additional sampling point to match existing on screw conveyors.
  • Fabricate and install platform extensions.
  • Install the cabling from existing substation to the SSA Anti-Caking Skid MCC.
  • Install the cabling from existing substation to the SSA Anti-Caking sump pump.
  • Install the level transmitter cable from the SSA Anti-Caking Skid sump to the analog input Charms module within the SSA Anti-Caking Skid MCC control section.